Stringybark Road Bridge: New Buderim-Sippy Downs Access Reaches Halfway Mark

Buderim and Sippy Downs residents will soon enjoy safer travel options as the new Stringybark Road bridge for pedestrians and cyclists hits the 50 per cent completion milestone, connecting the communities across the Sunshine Motorway.



The new three-metre-wide bridge runs parallel to the existing Stringybark Road vehicle bridge. It will provide a dedicated shared pathway for cyclists and pedestrians, separate from vehicle traffic.

Queensland Bridge and Civil, an experienced contractor, is overseeing the construction. The project aims to finish by November 2024, weather permitting.

Construction Progress

August 2024 marks a significant step forward with the installation of the new Stringybark Road Bridge deck. Twelve pre-made concrete beams will be lifted into place by crane and joined to form the deck. Temporary barriers will ensure a safe work environment during this process.

Day and night works are now underway to keep the project on schedule. The construction team is focusing on completing the bridge deck over the Sunshine Motorway, which forms a crucial part of the shared pedestrian and cycle pathway.

Additional Improvements

Once the new pedestrian and cycle bridge is complete, the existing vehicle bridge will change. The current pedestrian pathway will be removed, and on-road cycle lanes will be added to both sides. This reconfiguration aims to improve safety for all road users, including motorists and cyclists who prefer to ride on the road.

The design includes decorative elements inspired by the local forest canopy and birdlife. These features will create interesting light patterns during the day and provide soft lighting at night for user safety. The architectural elements are designed to complement the surrounding area, enhancing the bridge’s visual appeal while serving its practical purpose.

Stringybark Road bridge
Photo Credit: SunshineCoastCouncil

Traffic Management

Throughout construction, traffic on Stringybark Road and the Sunshine Motorway will remain open. However, drivers should be aware of some changes:

1. Single lane closures on the Sunshine Motorway at times

2. A temporary 80 km/h transition zone between the 100 km/h and 60 km/h areas near the construction site

3. Speed cameras in operation

Authorities will fine drivers who fail to follow these new traffic conditions. These measures are in place to ensure the safety of both construction workers and motorists during the project.

The existing shared pathway on the vehicle bridge will stay open for pedestrians and cyclists until the new bridge is ready, ensuring continuous access for non-motorised traffic.

Stringybark Road bridge
Photo Credit: SunshineCoastCouncil

Community Benefits

“The new 3m-wide ‘missing link’ spans the Sunshine Motorway, bridging the Division 6 and 7 communities. The separation of both bridges ensures all users can cross over the motorway safely, encouraging people of all ages and abilities to adopt more sustainable methods of transport,” Cr Ted Hungerford said.



The new Stringybark Road Bridge is expected to enhance community connectivity, promote active lifestyles, and provide a safer alternative for those walking or cycling between Buderim and Sippy Downs.

The $11.8-million project, jointly funded by the Queensland Government’s Cycle Network Local Government Grants program and Sunshine Coast Council, began construction in early March 2024.

Published 30-Aug-2021