A major renewal of the Maroochydore Wastewater Treatment Plant is underway, with critical equipment being upgraded to maintain essential services for households across Buderim, Maroochydore and surrounding Sunshine Coast communities. Every time someone flushes a toilet, empties a sink or runs a washing machine, wastewater begins a journey through an underground network that most residents rarely think about.
For households in Buderim and Maroochydore, much of that wastewater eventually reaches the Maroochydore Wastewater Treatment Plant, where millions of litres are processed each day before the treated water and remaining solids are managed.
Keeping the facility running requires constant maintenance, particularly as equipment ages and demand changes across the Sunshine Coast. Unitywater has embarked on a five-year renewal program targeting some of the plant’s most important operating systems, with work taking place while the facility continues treating wastewater.
From Buderim’s Drains to Maroochydore
The plant serves a much larger area than its name suggests. Along with Maroochydore, its service area includes Buderim, Sippy Downs, Bli Bli, Forest Glen, Pacific Paradise, Mudjimba, Kawana and Mountain Creek.
Approximately 147,000 residents rely on the facility, which processes around 11 billion litres of wastewater annually. Spread across the year, that works out to roughly 30 million litres a day.
The scale helps explain why renewing an operating wastewater plant is a substantial undertaking. Equipment needs to be replaced or reconfigured while the treatment processes continue around it.
The project forms part of Unitywater’s broader $500 million replacements and renewals program covering water and wastewater infrastructure over five years.
Major Works Across the Treatment Process
One of the first areas being renewed is the plant’s inlet works, where wastewater arrives from the sewer network.
At this stage, debris, grit, fats and other unwanted materials are removed before the wastewater proceeds through further treatment. Unitywater is reconfiguring this equipment as part of the works.
The project also includes renewing secondary clarifiers, which allow sludge to settle and separate from the wastewater, and one of the facility’s bioreactors. These bioreactors rely on microorganisms to break down waste and remove nutrients.
Unitywater Executive Manager Sustainable Infrastructure Solutions Mike Basterfield said the organisation had reconsidered how best to modernise the facility, moving away from more extensive and expensive upgrade options.
“The impressive part of this project has been the change in our approach that allowed us to move away from more extensive and costly upgrade options, towards a large-scale renewal program that has delivered significant savings—while keeping the plant operational for our customers,” Mr Basterfield said.
The works are being delivered by Unitywater’s delivery partner, Abergeldie.
A Second Life for Wastewater Sludge
Treating wastewater also produces sludge, which must undergo further processing.
At Maroochydore, the plant’s solar dryer is receiving a major renewal. The equipment removes moisture from sludge to produce biosolids, a treated material that can have beneficial uses in agriculture.
Mr Basterfield said the solar dryer was an important part of the treatment process, helping convert a wastewater by-product into material that can be used as fertiliser.
Agricultural reuse is subject to appropriate treatment, quality standards and regulatory requirements. The renewal announcement does not specify where biosolids produced at Maroochydore are ultimately used.
Renewal Rather Than Replacement
The renewal comes as the Sunshine Coast continues to accommodate residential and commercial development, placing ongoing demands on essential infrastructure.
For established communities such as Buderim, maintaining existing treatment facilities is just as important as providing infrastructure for newer development areas.
Maroochydore Wastewater Treatment Plant: Key Figures
Source: Unitywater, 6 July 2026. Daily processing volume calculated from the reported annual total. The $500 million allocation covers Unitywater’s broader renewal program, not solely this plant.
Unitywater said its planning, operations and capital delivery teams had worked together to identify ways to improve the plant’s performance without pursuing a more extensive redevelopment.
The company has also outlined a wider $2 billion investment program for critical water and wastewater infrastructure across its Sunshine Coast, Noosa and Moreton Bay service region.
However, the July 2026 announcement does not provide a separate cost for the Maroochydore project, a detailed construction timetable or a confirmed completion date.
For local households, the renewal may pass largely unnoticed. The work takes place behind the scenes, with the objective of keeping wastewater treatment reliable while major components of the plant are renewed.