Sunshine Coast Council recently issued a notice about upcoming traffic changes at Smith Street, Mooloolaba as Brisbane Road Car Park’s $18 million major overhaul progresses.
A section of Smith Street, between First Avenue and Muraban Street, will be periodically closed, from mid-February to early October 2020. Signage and traffic controllers will be present during these closures. Current woks involve:
- Delivering large quantities of reinforced steel and concrete
- Pouring concrete floor slabs, columns and walls for the new multi-deck car park
- Use of long reach mobile concrete pumps spanning the full width of Smith Street
Because of the work going on, residents and nearby businesses should expect construction noise with increased levels expected when the concrete pump is in operation. Reduced speed limits and changed traffic conditions will be in place. Additional truck movements should also be expected as concrete trucks arrive and depart from the construction site.
Depending on weather and site conditions, the construction of multi-deck car park is expected to be completed by December 2020. Construction hours will primarily be between 6:30 am – 6:30 pm, Monday to Saturday.
About Brisbane Road Car Park
The new eight-storey multi-deck car park will increase public parking on the site from 176 spaces to more than 700 car parking spaces, with a further 54 motorcycle spaces and 50 bicycle spaces.
Design rendered by Evans Built showed it drew inspiration from the natural environment and incorporates local references of the Mooloolaba area and the Placemaking Mooloolaba Masterplan.
Based on the Council’s timeframe, works will commence on the eight-storey building structure by early March 2020 to late March 2020. During construction, Council provides a range of free on-street and off-street parking throughout Mooloolaba